Open tendering of construction works
A 'tender' is a submission made by a prospective supplier in response to an invitation to tender. It makes an offer for the supply of goods or services. In construction, the main tender process is generally the selection, by the client, of a contractor to construct the works. However, procurement routes have become more complex, so tenders may now be sought for a wide range of goods and services.
Irrespective of the goods or services that are being sought, securing tenders generally follows one of a number of basic procedures:
Open tendering allows anyone to submit a tender to supply the goods or services that are required. Generally, an advert will be placed giving notice that the contract is being tendered, offering an equal opportunity to any organisation to submit a tender.
On larger projects, there may then be a pre-qualification process that produces a short-list of suitable suppliers from the respondents expressing interest in the contract. This short list will then be invited to prepare tenders. The selection of a short list can include pre-qualification questionnaires and interviews. This sort of pre-qualification process is not the same as selective tendering. Selective tendering only allows suppliers invited from a pre-selected list to take part in the tender process.
Open tendering has been criticised for being a slow and costly process, attracting tenders or expressions of interest from large numbers of suppliers, some of whom may be entirely unsuitable for the contract and as a result it can waste a great deal of time, effort and money. However, open tendering offers the greatest competition and has the advantage of allowing new or emerging suppliers to try to secure work and so can facilitate greater innovation. The number of firms tendering can be reduced (ideally to a maximum of 6) by a pre-qualification process, and if this uses a standard pre-qualification questionnaire, then the time wasted by unsuitable applicants can be minimised.
Whilst often seen to be more efficient, selective tendering can exclude potential suppliers, it can be seen to introduce bias into the process, and it can result in prospective suppliers continually contacting clients and consultants to check that they are on the appropriate lists.
On public projects, or projects that include an element of public funding, it may be necessary to advertise contracts as a requirement of the Public Contracts Regulations. This is intended to open up public procurement within the European Union and to ensure the free movement of supplies, services and works (see OJEU for more information).
Open tendering can be either single stage or two stage. Two-stage tendering is used to allow early appointment of a supplier, prior to the completion of all the information required to enable them to offer a fixed price. In the first stage, a limited appointment is agreed, allowing them to begin work and ine a fixed price is negotiated for the contract.
For a more detailed description of the procedures for open tendering, see Tender.
[edit] Related articles on Designing Buildings
- Appointing consultants.
- Call-off contract.
- Due diligence when selecting contractors or subcontractors.
- E-tendering.
- Invitation to tender.
- Mid-tender Interviews.
- OJEU procurement rules.
- Pre-qualification questionnaire.
- Pre-tender Interviews.
- Procurement routes.
- Reverse auction.
- Selective tender.
- Tender documentation.
- Tender evaluation.
- Tender processes for construction contracts
- Tender.
- Two stage tender.
Featured articles and news
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.